Capabilities

Capabilities menu
Capabilities

Capabilities that build America’s infrastructure.

About

About menu
About

Reaffirming innovation, quality, service, and safety since 1960.

Media

Signpost image for media top navigation link
Media

See Primoris’ latest News and Awards.

Careers

Two Primoris workers in safety vests looking at a crane
Careers

Providing unmatched personal and professional success.

Project Library

Filter by:
Capital Rail Constructors Metro Silver Line Extension
R.B. Hinkle completed a 10 mile trench in hard, dense shale soil.

Capital Rail Constructors Metro Silver Line Extension

R.B. Hinkle completed a 10 mile trench in hard, dense shale soil.

R.B. Hinkle completed a 10 mile trench in hard, dense shale soil.

R.B. Hinkle completed a 10 mile trench in hard, dense shale soil.

Enterprise M2E3 Seg. 4 & 7
Rockford completed a total of 134 miles of 36-inch pipeline as part of the M2E3 project.
#Pipeline
Burnet & Houston, TX

Enterprise M2E3 Seg. 4 & 7

Rockford completed a total of 134 miles of 36-inch pipeline as part of the M2E3 project. Segment 4 was laid in mostly dense rock formations that required blasting and rock trenching while Segment 7 was very congested, running through pipeline corridors south of Houston. Included in Rockford's scope were 26 horizontal directional drills, 188 bores, and 15 mainline valves. Welding was performed using a combination of CRC's automatic welding system and manual stick rod.

Rockford completed a total of 134 miles of 36-inch pipeline as part of the M2E3 project. Segment 4 was laid in mostly dense rock formations that required blasting and rock trenching while Segment 7 was very congested, running through pipeline corridors south of Houston. Included in Rockford's scope were 26 horizontal directional drills, 188 bores, and 15 mainline valves. Welding was performed using a combination of CRC's automatic welding system and manual stick rod.
Rockford completed a total of 134 miles of 36-inch pipeline as part of the M2E3 project. Segment 4 was laid in mostly dense rock formations that required blasting and rock trenching while Segment 7 was very congested, running through pipeline corridors south of Houston. Included in Rockford's scope were 26 horizontal directional drills, 188 bores, and 15 mainline valves. Welding was performed using a combination of CRC's automatic welding system and manual stick rod.
Florida South East Connection Project
Rockford constructed 77 miles of 36-inch and 49 miles of 30-inch for a total of 126 miles of pipeline from Lake Wales, FL to Okeechobee, FL.
#Pipeline
Okeechobee, FL

Florida South East Connection Project

Rockford constructed 77 miles of 36-inch and 49 miles of 30-inch for a total of 126 miles of pipeline from Lake Wales, FL to Okeechobee, FL. The project included 12 directional drills totaling 25,637 feet, 63 road bores totaling 8,089 feet, 30 open-cut roads, an interconnect, and a large meter station at the south end of the project. There were 5 successful mainline test sections to complete the project.

Rockford constructed 77 miles of 36-inch and 49 miles of 30-inch for a total of 126 miles of pipeline from Lake Wales, FL to Okeechobee, FL. The project included 12 directional drills totaling 25,637 feet, 63 road bores totaling 8,089 feet, 30 open-cut roads, an interconnect, and a large meter station at the south end of the project. There were 5 successful mainline test sections to complete the project.
Rockford constructed 77 miles of 36-inch and 49 miles of 30-inch for a total of 126 miles of pipeline from Lake Wales, FL to Okeechobee, FL. The project included 12 directional drills totaling 25,637 feet, 63 road bores totaling 8,089 feet, 30 open-cut roads, an interconnect, and a large meter station at the south end of the project. There were 5 successful mainline test sections to complete the project.
Rancho Pipeline Expansion Project
The Rancho Pipeline Expansion Project for Enterprise Products included the construction of 86 miles of 36-inch pipeline near Houston, TX.
#Pipeline
Houston, TX

Rancho Pipeline Expansion Project

The Rancho Pipeline Expansion Project for Enterprise Products included the construction of 86 miles of 36-inch pipeline near Houston, TX. A total of 18 horizontal directional drills, 14,600 feet of bores, and the placement 62,000 timber mats were needed to complete the project.

The Rancho Pipeline Expansion Project for Enterprise Products included the construction of 86 miles of 36-inch pipeline near Houston, TX. A total of 18 horizontal directional drills, 14,600 feet of bores, and the placement 62,000 timber mats were needed to complete the project.
The Rancho Pipeline Expansion Project for Enterprise Products included the construction of 86 miles of 36-inch pipeline near Houston, TX. A total of 18 horizontal directional drills, 14,600 feet of bores, and the placement 62,000 timber mats were needed to complete the project.
Rockies Express Project
Rockford constructed 31.4 miles of 42-inch in OH for Kinder Morgan/Conoco Phillips.
#Pipeline
Zanesville, OH

Rockies Express Project

Rockford constructed 31.4 miles of 42-inch in OH for Kinder Morgan/Conoco Phillips.

Rockford constructed 31.4 miles of 42-inch in OH for Kinder Morgan/Conoco Phillips.
Rockford constructed 31.4 miles of 42-inch in OH for Kinder Morgan/Conoco Phillips.
Ruby Project
Rockford constructed Spreads 6 and 7 of the Ruby Pipeline Project for El Paso Natural Gas which ran from Vya, NV to Malin, OR.
#Pipeline
Oregon & Nevada

Ruby Project

Rockford constructed Spreads 6 and 7 of the Ruby Pipeline Project for El Paso Natural Gas which ran from Vya, NV to Malin, OR. Totaling 127 miles of 42-inch pipeline, this challenging project included winter work, multiple winch line hills, large waterbody crossings, and the utilization of over one million pounds of dynamite for the excavation of both grade and ditch rock.

Rockford constructed Spreads 6 and 7 of the Ruby Pipeline Project for El Paso Natural Gas which ran from Vya, NV to Malin, OR. Totaling 127 miles of 42-inch pipeline, this challenging project included winter work, multiple winch line hills, large waterbody crossings, and the utilization of over one million pounds of dynamite for the excavation of both grade and ditch rock.
Rockford constructed Spreads 6 and 7 of the Ruby Pipeline Project for El Paso Natural Gas which ran from Vya, NV to Malin, OR. Totaling 127 miles of 42-inch pipeline, this challenging project included winter work, multiple winch line hills, large waterbody crossings, and the utilization of over one million pounds of dynamite for the excavation of both grade and ditch rock.
Sabal Trail - Spread 6
Rockford constructed Spread 6 of the Sabal Trail Pipeline Project as well as the Hunter Creek Lateral for Spectra which consisted of 76.6 miles of 36-inch pipeline.
#Pipeline
Center Hill, FL

Sabal Trail - Spread 6

Rockford constructed Spread 6 of the Sabal Trail Pipeline Project as well as the Hunter Creek Lateral for Spectra which consisted of 76.6 miles of 36-inch pipeline that ran from Near Wildwood, FL south to Kissimmee, FL. Included in this project were 6 horizontal directional drills, 30 road bores, 6 mainline valves, and the utilization of 135,000 timber mats.

Rockford constructed Spread 6 of the Sabal Trail Pipeline Project as well as the Hunter Creek Lateral for Spectra which consisted of 76.6 miles of 36-inch pipeline that ran from Near Wildwood, FL south to Kissimmee, FL. Included in this project were 6 horizontal directional drills, 30 road bores, 6 mainline valves, and the utilization of 135,000 timber mats.
Rockford constructed Spread 6 of the Sabal Trail Pipeline Project as well as the Hunter Creek Lateral for Spectra which consisted of 76.6 miles of 36-inch pipeline that ran from Near Wildwood, FL south to Kissimmee, FL. Included in this project were 6 horizontal directional drills, 30 road bores, 6 mainline valves, and the utilization of 135,000 timber mats.
Williams Midstream Various Projects
Rockford constructed over 125 miles of 8-inch to 24-inch in PA for Williams Midstream.
#Pipeline
Pennsylvania

Williams Midstream Various Projects

Rockford constructed over 125 miles of 8-inch to 24-inch in PA for Williams Midstream.

Rockford constructed over 125 miles of 8-inch to 24-inch in PA for Williams Midstream.
Rockford constructed over 125 miles of 8-inch to 24-inch in PA for Williams Midstream.
Anderson Dam Tunnel Project
This project involves a complicated, single microtunnel drive with the installation of 372 feet of 96-inch diameter steel casing pipe.
#Pipeline
Morgan Hill, CA

Anderson Dam Tunnel Project

This project involves a complicated, single microtunnel drive with the installation of 372 feet of 96-inch diameter steel casing pipe launched from a chamber tunneled under the Anderson Dam and recovered in the Anderson Reservoir. The microtunnel boring machine (MTBM) lake tap is launched from inside of a 24-foot Horseshoe tunnel mined chamber under the Anderson Dam, this 1,600-foot conventional tunnel will incorporate steel horseshoes and a reinforced concrete lining. A reaction frame and portal launch seal are used to tunnel from the chamber to a lake tap Landing pad deep below the surface of the Anderson Reservoir where the MTBM is recovered using specialty divers, barges, and cranes.

This project involves a complicated, single microtunnel drive with the installation of 372 feet of 96-inch diameter steel casing pipe launched from a chamber tunneled under the Anderson Dam and recovered in the Anderson Reservoir. The microtunnel boring machine (MTBM) lake tap is launched from inside of a 24-foot Horseshoe tunnel mined chamber under the Anderson Dam, this 1,600-foot conventional tunnel will incorporate steel horseshoes and a reinforced concrete lining. A reaction frame and portal launch seal are used to tunnel from the chamber to a lake tap Landing pad deep below the surface of the Anderson Reservoir where the MTBM is recovered using specialty divers, barges, and cranes.
This project involves a complicated, single microtunnel drive with the installation of 372 feet of 96-inch diameter steel casing pipe launched from a chamber tunneled under the Anderson Dam and recovered in the Anderson Reservoir. The microtunnel boring machine (MTBM) lake tap is launched from inside of a 24-foot Horseshoe tunnel mined chamber under the Anderson Dam, this 1,600-foot conventional tunnel will incorporate steel horseshoes and a reinforced concrete lining. A reaction frame and portal launch seal are used to tunnel from the chamber to a lake tap Landing pad deep below the surface of the Anderson Reservoir where the MTBM is recovered using specialty divers, barges, and cranes.
Davis Lane Lift Station Microtunnel
This project consisted of a single microtunnel drive of 696 feet of 64-inch diameter x 0.75-inch wall Trinity Products Tri-Loc Weldless Steel Casing.
#Pipeline
Bozeman, MT

Davis Lane Lift Station Microtunnel

This project consisted of a single microtunnel drive of 696 feet of 64-inch diameter x 0.75-inch wall Trinity Products Tri-Loc Weldless Steel Casing. The microtunnel was installed under two frontage roads, an active railroad, and four lanes of Interstate 90 progressing through silts, sands, gravels, cobbles, and boulders beneath the groundwater table.

This project consisted of a single microtunnel drive of 696 feet of 64-inch diameter x 0.75-inch wall Trinity Products Tri-Loc Weldless Steel Casing. The microtunnel was installed under two frontage roads, an active railroad, and four lanes of Interstate 90 progressing through silts, sands, gravels, cobbles, and boulders beneath the groundwater table.
This project consisted of a single microtunnel drive of 696 feet of 64-inch diameter x 0.75-inch wall Trinity Products Tri-Loc Weldless Steel Casing. The microtunnel was installed under two frontage roads, an active railroad, and four lanes of Interstate 90 progressing through silts, sands, gravels, cobbles, and boulders beneath the groundwater table.
Holmes Road Project
This project consists of installing fiberglass reinforced pipe (FRP) sanitary sewer totaling approximately 3,600 feet of 42-inch diameter and 990 feet of 48-inch diameter.
#Pipeline
Houston, TX

Holmes Road Project

This project consists of installing fiberglass reinforced pipe (FRP) sanitary sewer totaling approximately 3,600 feet of 42-inch diameter and 990 feet of 48-inch diameter. The pipe installation is completed in five separate tunnel drives all at approximately 30 to 35 feet in depth with the tunnel reaches varying from approximately 700 feet to 1,000 feet. The entirety of the project is below the natural groundwater table through soils that are saturated with contaminated water requiring extensive coordination with the City of Houston to provide water-tight shafts and mitigate all potential environmental impacts.

This project consists of installing fiberglass reinforced pipe (FRP) sanitary sewer totaling approximately 3,600 feet of 42-inch diameter and 990 feet of 48-inch diameter. The pipe installation is completed in five separate tunnel drives all at approximately 30 to 35 feet in depth with the tunnel reaches varying from approximately 700 feet to 1,000 feet. The entirety of the project is below the natural groundwater table through soils that are saturated with contaminated water requiring extensive coordination with the City of Houston to provide water-tight shafts and mitigate all potential environmental impacts.
This project consists of installing fiberglass reinforced pipe (FRP) sanitary sewer totaling approximately 3,600 feet of 42-inch diameter and 990 feet of 48-inch diameter. The pipe installation is completed in five separate tunnel drives all at approximately 30 to 35 feet in depth with the tunnel reaches varying from approximately 700 feet to 1,000 feet. The entirety of the project is below the natural groundwater table through soils that are saturated with contaminated water requiring extensive coordination with the City of Houston to provide water-tight shafts and mitigate all potential environmental impacts.
PG&E R-985 Project
This project consists of installing 140 feet of 24-inch diameter sacrificial steel casing using microtunnel.
#Pipeline
Millbrae, CA

PG&E R-985 Project

This project consists of installing 140 feet of 24-inch diameter sacrificial steel casing using microtunnel beneath an existing concrete-lined channel and storm drain/sanitary sewer while providing a minimum depth of cover of 18 feet below the channel bottom and 10 feet of vertical separation from an existing 33-inch storm drain. Shafts for microtunnel work were approximately 35 feet deep and the microtunnel progressed through primarily sandy soils approximately 30 feet below the groundwater table utilizing the sacrificial case-and-displace method with steel casing pipe to install the steel gas pipe.

This project consists of installing 140 feet of 24-inch diameter sacrificial steel casing using microtunnel beneath an existing concrete-lined channel and storm drain/sanitary sewer while providing a minimum depth of cover of 18 feet below the channel bottom and 10 feet of vertical separation from an existing 33-inch storm drain. Shafts for microtunnel work were approximately 35 feet deep and the microtunnel progressed through primarily sandy soils approximately 30 feet below the groundwater table utilizing the sacrificial case-and-displace method with steel casing pipe to install the steel gas pipe.
This project consists of installing 140 feet of 24-inch diameter sacrificial steel casing using microtunnel beneath an existing concrete-lined channel and storm drain/sanitary sewer while providing a minimum depth of cover of 18 feet below the channel bottom and 10 feet of vertical separation from an existing 33-inch storm drain. Shafts for microtunnel work were approximately 35 feet deep and the microtunnel progressed through primarily sandy soils approximately 30 feet below the groundwater table utilizing the sacrificial case-and-displace method with steel casing pipe to install the steel gas pipe.